INSTALLATION
Pressure Relief Port Installation
Simple Installation. Reliable Performance.
The Explovent Relief Port is designed for straightforward installation into insulated cold room, freezer room and blast chiller panels. The process requires only a suitable penetration, correct positioning and electrical connection by a licensed electrician.

The overview below outlines the standard installation process.
Step 1
Cut Penetration
Using the appropriate hole saw or panel cutting method, create a penetration matching the selected Explovent Relief Port size.
Ensure:
- The cut is clean and free from damage
- The penetration matches the specified model diameter
- Surrounding panel materials remain intact
A correctly sized penetration helps ensure proper fitment and sealing.
Step 2
Insert & Seal
Insert the Explovent Relief Port through the panel from the external side toward the internal side.
Once positioned:
- Align the unit correctly
- Secure the assembly
- Apply suitable sealing methods around the penetration
- Verify the unit sits flush against the panel surface
Proper sealing helps maintain panel integrity and prevent unwanted air leakage.
Step 3
Check Electrical
Before completing installation, inspect the electrical tail and wiring.
Ensure:
- Wiring is free from damage
- Connections remain dry and protected
- Cable routing avoids sharp edges or abrasion points
The electrical heater assists reliable operation by reducing the risk of ice buildup around the relief mechanism.
Step 4
Cover & Connect
Install the cover plate and complete final sealing.
Electrical connection must be completed by a licensed electrician in accordance with Australian standards.
Once connected:
- Verify operation
- Confirm all fasteners are secure
- Check seals are intact
- Ensure the relief mechanism moves freely
The unit is now ready for operation.
Recommended Installation Location
For best performance, pressure relief ports are typically installed:
- High on a wall or ceiling
- Away from direct evaporator airflow
- In a position that allows unrestricted pressure equalisation
- Where future inspection and maintenance can be easily performed
Correct positioning helps minimise ice formation and supports consistent pressure equalisation.
Important Heater Activation Notice
Do not activate the heater element until the cold room has reached its intended operating temperature.
Activating the heater too early during commissioning can expose surrounding materials to unnecessary heat and may damage plastics or adjacent panel materials.
Always complete commissioning in accordance with the supplied product instructions.
Installation Benefits
Once installed, the Explovent Relief Port helps:
- Equalise pressure during door operation
- Equalise pressure during temperature changes
- Reduce stress on insulated panels
- Protect atmospheric seals
- Reduce ice buildup
- Support efficient refrigeration operation